End dates of Subtask are appearing wrong
Hi there, I'm facing issue with import of xml file. When I import the file, Finish date of task having subtask, gets disturb. I am attaching the screenshot from xml file indicating the dates that I have set in it Heres the screenshot from Microsoft Project when I import the xml file After going through multiple solution, I found one of them partially working which suggested that i should turn off project calculation after each edit After applying this setting and re-loading the xml, Finish date of parent task appear corrected but for its subtasks which has duration greater than one, it still appears wrong Can someone please suggest me a solution for this ?136Views0likes3Comments